What the hours cover
Breaker, home run, one box and device at the far end, terminate, test, and label the directory. The kitchen counter line is the same thing priced as a unit on a larger rewire, with the access already open.
The math at the book numbers
The labor factor is the overhead multiplier divided by one minus the target margin. At 1.35 and 20 percent that is 1.69.
Add new circuit, 15A or 20A. 2.5 hours × $135 × 1.69 is $569.53 of labor. $28 of material × 1.30 is $36.40. Together that is $605.93, rounded to $610.
Dedicated kitchen counter circuit. 1.5 hours × $135 × 1.69 is $341.72 of labor. $25 of material × 1.30 is $32.50. Together that is $374.22, rounded to $370.
Better is the Good price times 1.25 and Best is times 1.55. Same job done better, not a different job.
Same job at three labor rates
| Job | $110 rate | $135 rate | $165 rate |
|---|---|---|---|
| Add new circuit, 15A or 20A | $500 | $610 | $730 |
| Dedicated kitchen counter circuit | $310 | $370 | $450 |
Good tier at each rate. Everything else left at the book numbers.
What moves this number
- Run length and what is in the way. A finished basement ceiling or a slab changes everything.
- No space in the panel.
- The breaker has to be AFCI, GFCI or dual function. Add that from its own line.
- Exterior or wet location boxes and covers.
Not in this price
Extra devices on the circuit, drywall repair, and the specialty breaker if one is required.
The full breakdown is in the guide: How to Price a Whole-Home Rewire.