What the hours cover

Mount the disconnect, land line and load conductors, bond it as the service equipment, and verify operation.

The math at the book numbers

(billable hours × loaded labor rate × labor factor) + (material cost × markup), rounded to the nearest $10

The labor factor is the overhead multiplier divided by one minus the target margin. At 1.35 and 20 percent that is 1.69.

Main disconnect. 3 hours × $135 × 1.69 is $683.44 of labor. $125 of material × 1.30 is $162.50. Together that is $845.94, rounded to $850.

Better is the Good price times 1.25 and Best is times 1.55. Same job done better, not a different job.

Same job at three labor rates

Tier$110 rate$135 rate$165 rate
Good$720$850$1,000
Better$900$1,060$1,250
Best$1,120$1,310$1,550

All three tiers at each rate. Everything else left at the book numbers.

What moves this number

  • Once the disconnect is the service equipment, the old main panel is a sub-panel. Neutrals and grounds have to come apart in it, and the feeder may need a fourth conductor.
  • Utility coordination for the shutdown and reconnect.
  • Exterior wall material. Brick and stucco are not the same hour as vinyl.
  • The jurisdiction wants an exterior emergency disconnect with specific labeling.

Not in this price

Separating neutrals and grounds in a crowded panel and replacing the feeder between the two. If you see that coming, add the hours before you quote.

The full breakdown is in the guide: How to Price a 200-Amp Service Upgrade.