What the hours cover
Mount the disconnect, land line and load conductors, bond it as the service equipment, and verify operation.
The math at the book numbers
The labor factor is the overhead multiplier divided by one minus the target margin. At 1.35 and 20 percent that is 1.69.
Main disconnect. 3 hours × $135 × 1.69 is $683.44 of labor. $125 of material × 1.30 is $162.50. Together that is $845.94, rounded to $850.
Better is the Good price times 1.25 and Best is times 1.55. Same job done better, not a different job.
Same job at three labor rates
| Tier | $110 rate | $135 rate | $165 rate |
|---|---|---|---|
| Good | $720 | $850 | $1,000 |
| Better | $900 | $1,060 | $1,250 |
| Best | $1,120 | $1,310 | $1,550 |
All three tiers at each rate. Everything else left at the book numbers.
What moves this number
- Once the disconnect is the service equipment, the old main panel is a sub-panel. Neutrals and grounds have to come apart in it, and the feeder may need a fourth conductor.
- Utility coordination for the shutdown and reconnect.
- Exterior wall material. Brick and stucco are not the same hour as vinyl.
- The jurisdiction wants an exterior emergency disconnect with specific labeling.
Not in this price
Separating neutrals and grounds in a crowded panel and replacing the feeder between the two. If you see that coming, add the hours before you quote.