What the hours cover
Mount the panel, install the feeder breaker in the main, pull a four wire feeder, land it with the neutrals and grounds kept separate, and label the directory.
The math at the book numbers
The labor factor is the overhead multiplier divided by one minus the target margin. At 1.35 and 20 percent that is 1.69.
Sub-panel, 100A. 5 hours × $135 × 1.69 is $1,139.06 of labor. $285 of material × 1.30 is $370.50. Together that is $1,509.56, rounded to $1,510.
Better is the Good price times 1.25 and Best is times 1.55. Same job done better, not a different job.
Same job at three labor rates
| Tier | $110 rate | $135 rate | $165 rate |
|---|---|---|---|
| Good | $1,300 | $1,510 | $1,760 |
| Better | $1,620 | $1,890 | $2,200 |
| Best | $2,010 | $2,340 | $2,730 |
All three tiers at each rate. Everything else left at the book numbers.
What moves this number
- Feeder length. The book figure assumes a short run. A sub-panel across the house or out in a garage is a different material number and a different day.
- No space in the main for the feeder breaker.
- A detached building. That adds trenching or an overhead run and its own grounding electrode.
- Finished walls and ceilings between the two panels.
Not in this price
The branch circuits that come out of the new panel. Price each one as a new circuit.