What the hours cover

Mount the panel, install the feeder breaker in the main, pull a four wire feeder, land it with the neutrals and grounds kept separate, and label the directory.

The math at the book numbers

(billable hours × loaded labor rate × labor factor) + (material cost × markup), rounded to the nearest $10

The labor factor is the overhead multiplier divided by one minus the target margin. At 1.35 and 20 percent that is 1.69.

Sub-panel, 100A. 5 hours × $135 × 1.69 is $1,139.06 of labor. $285 of material × 1.30 is $370.50. Together that is $1,509.56, rounded to $1,510.

Better is the Good price times 1.25 and Best is times 1.55. Same job done better, not a different job.

Same job at three labor rates

Tier$110 rate$135 rate$165 rate
Good$1,300$1,510$1,760
Better$1,620$1,890$2,200
Best$2,010$2,340$2,730

All three tiers at each rate. Everything else left at the book numbers.

What moves this number

  • Feeder length. The book figure assumes a short run. A sub-panel across the house or out in a garage is a different material number and a different day.
  • No space in the main for the feeder breaker.
  • A detached building. That adds trenching or an overhead run and its own grounding electrode.
  • Finished walls and ceilings between the two panels.

Not in this price

The branch circuits that come out of the new panel. Price each one as a new circuit.

The full breakdown is in the guide: How to Price a 200-Amp Service Upgrade.