What the hours cover
Power down, pull the old panel, set the new one, re-land and label every branch circuit, bring the grounding and bonding up to what the inspector wants today, then inspection and re-energize.
The math at the book numbers
The labor factor is the overhead multiplier divided by one minus the target margin. At 1.35 and 20 percent that is 1.69.
Federal Pacific or Zinsco swap. 8 hours × $135 × 1.69 is $1,822.50 of labor. $485 of material × 1.30 is $630.50. Together that is $2,453, rounded to $2,450.
Better is the Good price times 1.25 and Best is times 1.55. Same job done better, not a different job.
Same job at three labor rates
| Tier | $110 rate | $135 rate | $165 rate |
|---|---|---|---|
| Good | $2,120 | $2,450 | $2,860 |
| Better | $2,640 | $3,070 | $3,570 |
| Best | $3,280 | $3,800 | $4,430 |
All three tiers at each rate. Everything else left at the book numbers.
What moves this number
- Bus stabs that are burned or breakers welded on. Getting the old interior out clean can take longer than setting the new one.
- Brittle cloth insulation and conductors that will not reach. Budget for splices in the gutter space or a junction box.
- Multiwire branch circuits that were never tied together. They have to be found and handled before you land them.
- The house sale. A lot of these come from an inspection report with a closing date attached, and rush work is not standard rate work.
Not in this price
A service size change is its own job. If the customer is going from 100A to 200A at the same time, price it on the service upgrade calculator, not here.
The full breakdown is in the guide: How to Price a 200-Amp Service Upgrade.