What the hours cover

Permit and utility coordination, the load calculation, demo and disconnect, the service entrance, setting the panel and landing every branch circuit, grounding and bonding, then the inspection and re-energize. That is one inspection and nothing ugly behind the wall.

The math at the book numbers

(billable hours × loaded labor rate × labor factor) + (material cost × markup), rounded to the nearest $10

The labor factor is the overhead multiplier divided by one minus the target margin. At 1.35 and 20 percent that is 1.69.

100A to 200A upgrade. 8 hours × $135 × 1.69 is $1,822.50 of labor. $485 of material × 1.30 is $630.50. Together that is $2,453, rounded to $2,450.

150A to 200A upgrade. 6 hours × $135 × 1.69 is $1,366.88 of labor. $385 of material × 1.30 is $500.50. Together that is $1,867.38, rounded to $1,870.

Better is the Good price times 1.25 and Best is times 1.55. Same job done better, not a different job.

Same job at three labor rates

Job$110 rate$135 rate$165 rate
100A to 200A upgrade$2,120$2,450$2,860
150A to 200A upgrade$1,610$1,870$2,170

Good tier at each rate. Everything else left at the book numbers.

What moves this number

  • The utility wants the meter socket moved or replaced, or their crew shows up at 3pm instead of 8am.
  • A correction and a second inspection. That is another trip with the customer sitting in the dark.
  • Branch conductors too short to reach the new lugs, double taps, or aluminum branch wiring nobody mentioned.
  • The grounding electrode system. A water bond on the far side of the basement is real time.

Not in this price

Surge protection, AFCI breakers, a generator interlock, and drywall or siding repair are separate lines. On an older house those add-ons can be bigger than the upgrade.

The full breakdown is in the guide: How to Price a 200-Amp Service Upgrade.