What the hours cover
Disconnect and remove the old furnace, set the new one, transition the plenum and return, reconnect gas or oil, vent, electrical and controls, then fire it and commission it.
The math at the book numbers
The labor factor is the overhead multiplier divided by one minus the target margin. At 1.4 and 22 percent that is 1.79.
Gas furnace, 80% AFUE. 6 hours × $135 × 1.79 is $1,453.85 of labor. $985 of material × 1.35 is $1,329.75. Together that is $2,783.60, rounded to $2,780.
Gas furnace, 96% AFUE. 6 hours × $135 × 1.79 is $1,453.85 of labor. $1,485 of material × 1.35 is $2,004.75. Together that is $3,458.60, rounded to $3,460.
Electric furnace. 5 hours × $135 × 1.79 is $1,211.54 of labor. $785 of material × 1.35 is $1,059.75. Together that is $2,271.29, rounded to $2,270.
Oil furnace. 8 hours × $135 × 1.79 is $1,938.46 of labor. $1,685 of material × 1.35 is $2,274.75. Together that is $4,213.21, rounded to $4,210.
Better is the Good price times 1.25 and Best is times 1.55. Same job done better, not a different job.
Same job at three labor rates
| Job | $110 rate | $135 rate | $165 rate |
|---|---|---|---|
| Gas furnace, 80% AFUE | $2,510 | $2,780 | $3,110 |
| Gas furnace, 96% AFUE | $3,190 | $3,460 | $3,780 |
| Electric furnace | $2,050 | $2,270 | $2,540 |
| Oil furnace | $3,850 | $4,210 | $4,640 |
Good tier at each rate. Everything else left at the book numbers.
What moves this number
- Going from 80 percent to a condensing furnace. New venting, an intake, and a condensate drain are not in six hours.
- A water heater left alone on an oversized chimney after the furnace stops using it.
- Sheet metal. A furnace with a different footprint means transitions on both ends.
- Permit and inspection time. None of it is in the hours and all of it happens.
Not in this price
Venting changes, chimney liners, gas line changes, duct modifications, and the permit fee.