What the hours cover

Recovery and removal, set the outdoor unit and the indoor coil or air handler, line set, electrical and controls, evacuation, charge, and commissioning in both heating and cooling.

The math at the book numbers

(billable hours × loaded labor rate × labor factor) + (material cost × markup), rounded to the nearest $10

The labor factor is the overhead multiplier divided by one minus the target margin. At 1.4 and 22 percent that is 1.79.

Heat pump, 3 ton. 8 hours × $135 × 1.79 is $1,938.46 of labor. $2,685 of material × 1.35 is $3,624.75. Together that is $5,563.21, rounded to $5,560.

Heat pump, 5 ton. 10 hours × $135 × 1.79 is $2,423.08 of labor. $3,685 of material × 1.35 is $4,974.75. Together that is $7,397.83, rounded to $7,400.

Better is the Good price times 1.25 and Best is times 1.55. Same job done better, not a different job.

Same job at three labor rates

Job$110 rate$135 rate$165 rate
Heat pump, 3 ton$5,200$5,560$5,990
Heat pump, 5 ton$6,950$7,400$7,940

Good tier at each rate. Everything else left at the book numbers.

What moves this number

  • Auxiliary heat. Strip heat needs its own circuit capacity and the panel may not have it.
  • Thermostat wiring. A heat pump needs more conductors than the old cooling only system had.
  • Cold climate and variable speed equipment. The cost is nowhere near the allowance.
  • Rebate paperwork. Somebody spends an hour on it and it is usually you.

Not in this price

Electrical upgrades, a new line set, duct modifications, the thermostat, and the permit fee.

The full breakdown is in the guide: How to Price a Full HVAC System Replacement.