Every electrician has priced a job in a driveway. You look at the panel, you think about the last one like it, you add a little for the attic, and you say a number. Sometimes it is right. You never find out which times.
This is the other way to do it. Sixteen common electrical jobs with the hours and the material on each line, and the Good, Better and Best price that comes out of them. Every number is built on the same formula the flat rate calculators on this site run, set up for a Philadelphia metro shop at a $135 loaded labor rate.
It is a worked example, not a survey of what everybody charges. Change the rate and every line moves, and electrical moves more than most trades. I will show you why further down.
How every price on this list is built
Price = (billable hours × loaded labor rate × labor factor) + (material cost × 1.30), rounded to the nearest $10.
- Loaded labor rate, $135. Wage plus payroll tax, comp, insurance, the truck, and the hours you spend quoting and driving that nobody pays for. If you have not worked yours out, the labor rate calculator does it.
- Labor factor, 1.69. A 1.35 overhead multiplier divided by one minus a 20 percent target margin. Leave it out and you are working for your overhead.
- Material markup, 30 percent on what you pay at the supply house.
- Better is Good times 1.25, Best is Good times 1.55. Same job done better, not a different job.
There is no minimum charge built into these lines, because most of them are big enough not to need one. Your dispatch fee still applies on a standalone call, and on the small ones, a surge protector or a single AFCI breaker, it matters.
Service and panel work
Click any job to open its calculator and put your own rate in.
| Job | Good | Better | Best |
|---|---|---|---|
| 100A to 200A service upgrade 8 hrs, $485 material | $2,450 | $3,070 | $3,800 |
| 150A to 200A service upgrade 6 hrs, $385 material | $1,870 | $2,330 | $2,890 |
| Federal Pacific or Zinsco panel replacement 8 hrs, $485 material | $2,450 | $3,070 | $3,800 |
| 100A sub-panel 5 hrs, $285 material | $1,510 | $1,890 | $2,340 |
| Main disconnect 3 hrs, $125 material | $850 | $1,060 | $1,310 |
| Whole house surge protector 1.5 hrs, $115 material | $490 | $610 | $760 |
Why the 200 amp upgrade here is $2,450 and not $7,460
If you have read what is inside the electrician book, you saw a 100A to 200A upgrade at $7,460. Both numbers are right. The $2,450 line is the upgrade itself: permit and utility coordination, the load calc, the service entrance, setting the panel, landing every circuit, grounding and bonding, one inspection and nothing ugly behind the wall.
The $7,460 is what the job usually turns into on an older house once the inspector asks for AFCI protection, the surge protector goes in and the rest of the code work gets done. Twelve AFCI breakers at $280 is $3,360 by itself. The 200 amp upgrade guide walks through it line by line. Quote the upgrade and the add-ons as separate lines and the customer can see exactly where the money goes.
Circuits and devices
| Job | Good | Better | Best |
|---|---|---|---|
| New 15A or 20A circuit 2.5 hrs, $28 material, per circuit | $610 | $760 | $940 |
| Kitchen counter circuit, on a larger rewire 1.5 hrs, $25 material, per circuit | $370 | $470 | $580 |
| AFCI breaker 1 hr, $40 material, per circuit | $280 | $350 | $430 |
| Dual function AFCI/GFCI breaker 1 hr, $55 material, per circuit | $300 | $370 | $460 |
| Hardwired interconnected smoke detector 1 hr, $32 material, each | $270 | $340 | $420 |
| Aluminum wiring pigtail 0.75 hrs, $8 material, per outlet | $180 | $230 | $280 |
The AFCI line is an hour and not ten minutes for a reason. Putting the breaker in is quick. Finding out why it trips, which on an older house it often does, is not. Price the hour, or eat it on every one that fights you.
Rewire work
| Job | Good | Better | Best |
|---|---|---|---|
| Bedroom rewire, average 6 hrs, $95 material, per room | $1,490 | $1,860 | $2,310 |
| Kitchen rewire, average 8 hrs, $145 material, per room | $2,010 | $2,510 | $3,120 |
| Bathroom rewire, average 4 hrs, $65 material, per room | $1,000 | $1,240 | $1,540 |
| Knob and tube replacement 4 hrs, $55 material, per circuit | $980 | $1,230 | $1,520 |
Living rooms and dining rooms price as a bedroom. A room line covers new home runs, new boxes where the old ones will not pass, new devices, and the old wiring made safe. It does not cover the service upgrade, smoke detectors, panel labeling or the wall repair. On a whole house those add up to thousands, which is why the whole-home rewire guide prices it room by room and then adds the extras on top.
What is not in these prices
- The trip on small jobs. The surge protector line assumes you are already there for panel or service work. On a standalone call, add your dispatch fee. The trip charge calculator will tell you what it should be.
- Drywall, plaster and paint. Say so on the estimate, every time.
- Whatever you find. The wiring fault behind a tripping AFCI. Boxes that fail box fill on a pigtail job. Branch conductors too short to reach the new lugs on a panel swap. Quote them once you know what they are.
- Branch circuits out of a new sub-panel. Price each one as a new circuit.
- After hours. Time and a half on the work, decided ahead of time.
What happens at your rate
The Good price for six of these jobs at three loaded rates, everything else left alone.
| Job, Good tier | $110 rate | $135 rate | $165 rate |
|---|---|---|---|
| 100A to 200A upgrade | $2,120 | $2,450 | $2,860 |
| 100A sub-panel | $1,300 | $1,510 | $1,760 |
| New 15A or 20A circuit | $500 | $610 | $730 |
| AFCI breaker, per circuit | $240 | $280 | $330 |
| Bedroom rewire | $1,240 | $1,490 | $1,790 |
| Knob and tube, per circuit | $810 | $980 | $1,190 |
Electrical is mostly labor. A bedroom rewire is $95 of material and six hours, so almost the whole price rides on your rate. Go from $110 to $165 and that room goes from $1,240 to $1,790. That is why the rate is the most important number in an electrician's book, and the first one to get right. If you have not worked yours out from your real overhead, start with this guide.
From a list to a book
Sixteen lines cover a lot of service work. They do not cover the call that turns into a generator interlock, an EV charger on a long run, recessed cans in a finished ceiling or a meter socket the utility wants replaced. A working book is a few hundred lines, every one built on the same rate so they agree with each other, and every one moving together when your costs change.
Use the list, use the book, or build your own. Just stop pricing in the driveway. The number you say out loud should be the one you would have written down at the kitchen table on a Sunday with the calculator in front of you.